Marking Standard Cost EstimatesYou can only mark cost estimates that have no errors. Such cost estimates have the status KA . Cost estimates with errors have the status KF . You cannot mark these.
The validity of the standard cost estimate corresponds with the current period in the material master.
Marking the standard cost estimate has been allowed .
To mark standard cost estimates in a costing run, see Costing Run: Marking for Standard Price .
Choose
The screen
Price Update: Mark Standard Price
appears.
Enter the posting period and fiscal year.
Enter the selection criteria for the cost estimate to be marked:
Company code(s)
If you do not enter any data, the system selects all the company codes in the controlling area.
Plant(s)
If you do not enter any data, the system selects either all the plants of the company code specified, or, if no company code has been specified, all the plants of all the company codes.
Material number(s)
If you do not enter any data, the system selects all the materials for marking.
If you do not enter any selection criteria, the system marks all the cost estimates in all the company codes of the controlling area for which marking is allowed.
Specify which valuation view is to be marked.
This step only applies if you want to cost multiple values (see Group Costing ).
Choose
Marking allowance
to display the allowance for marking or to issue the allowance. ( See also
Allowing Marking
)
The screen
Price Update: Organizational Measure
appears. For more information, see
Allowing Marking
. Choose
to return to the marking.
By setting the corresponding indicator, you determine whether:
Marking should first take place in the test run
A list of the cost estimates to be marked should be issued
Marking should take place using parallel processing
Marking should take place in the background
Choose
to execute marking.
Note
If you have set the indicator
Background processing
, marking is not carried out immediately. The system next displays the dialog box
Background Processing: Job Parameters.
Set the indicator
Immediate start
if you want to start marking immediately in the background, or enter the date from which the job should be started. Choose
Date/Time
to enter an exact start date
After job
or
After event
to specify that marking should not start until after the completion of another job or after a particular event
Copy
to save your entries and schedule the job
or
to display an overview of all jobs
For more information, see Background Processing .
If you carried out marking online but did not set the indicator
With list
, the system issues a message containing the information as to how many standard cost estimates were marked successfully or had errors.
If you carried out marking online and set the indicator
With list
, the system displays a list of materials that were marked or, in the case of a test run, will be marked.
This list can easily be adapted to suit your requirements. For more information, see Functions of the ABAP List Viewer .
If you choose
in this list, you can go to the log containing the system messages. You can also edit this log and adapt it to your requirements. To go to the long text of a message, place the cursor on the desired line and choose
. To go back to the list of marked materials, choose
in the toolbar of the log. For more information, see
Logs in Material Costing
.
To return to the screen
Price Update: Mark Standard Price
, choose
in the application menu. If you choose
Log
in this screen, you can call the log which you last generated once again.
After marking, the results of the standard cost estimate are updated as the future standard price in the material master (accounting view and costing view). Marking does not affect the material stock value.
In a further step, you can now release the results of the standard cost estimate in the material master record as the current standard price.
Note
Provided no standard cost estimate has been released, you can cancel both the allowance for marking and the marking which has already been carried out. All marking in the selected company code will then be canceled. For the procedure, see Allowing Marking.